Richmond Malt

Project Details

Client

Probuild

Address

2 Gough Street Cremorne

Basement Levels

2

Engineered piling pad (m2)

1350

Piles

211 retention and foundation piles to 12 mbgs

Ground Anchors

130

Capping beam (l/m)

270

Shotcrete (m2)

1700

Environmental Remediation Summary

Onsite abatement of ~5,000m3 of asbestos contaminated soil. Completion of part of the excavation works under asbestos conditions. Track, load, cart, and dispose ~5,000m3 of chemically contaminated fill post abatement. Gas freeing, emptying and removal of two underground storage tanks (UST), validation and reporting of the UST tank pits prior to further excavation. All remedial works were conducted under environmental audit and the site validated to satisfy the Environmental Auditor to develop the site.

Bulk and Detailed Excavation

~60,000 metres of basaltic clay and break out of basalt rock